| 1. |
Structure |
: |
RCC frame structure with footings, columns, beams, Slab etc to Kristal Design
|
| |
|
|
|
| 2. |
Walls |
: |
6” Solid / HollowBlock Masonry for External walls & 4" Solid / Hollow Block Masonry for Internal walls. |
| |
|
|
|
| 3. |
Doors |
: |
Main Door: Teak wood frame and teak wood shutter with Polish on both sides; Black & Décor Locks or equivalent lock with Brass fittings and stopper.Other Doors: Hardwood frame with Designed moulded shutter with imported skin on one side and paint on the other side with Black & Decor or Equivalent lock and brass fittings. |
| |
|
|
|
| 4. |
Windows |
: |
Anodized /Powder coated Aluminum three track with Wooden frames with glass in two tracks and GI mosquito mesh in one track. |
| |
|
|
|
| 5. |
Flooring |
: |
Vitrified Tiles with / without spacer filled with tiles filler with Epoxy coating flooring for living / dining & Bed rooms (Basic cost of Tile Rs.55/ Sft) & 12”x12” ceramic flooring in kitchen, with 4" skirting. Ceramic flooring in Toilets (Basic Price of Tile Rs.22 / Sft). |
| |
|
|
|
| 6. |
Kitchen |
: |
20mm thick polished granite slab over RCC platform with stainless steel sink with drain board and 2' height light colour Ceramic dadoing.(Basic Price of Tile Rs.22/ Sft) |
| |
|
|
|
| 7. |
Toilets |
: |
Ceramic tile dadoing (Light color) of 7’ height (Basic Price of Tile Rs. 22/- Sft), Concealed CPVC/PVC/GI pipe lining with Crab Tree / Ideal Orient/ Equivalent brand CP fittings and Cera brand white color ceramic fittings. Wash basin (without pedestals). |
| |
|
|
|
| 8. |
Plastering |
: |
Internal Walls and Ceiling: Neeru finish with 2 coats of Premier Emulsion over one coat of wall Primer and one coat of putty. (Brush Finish) External walls: Sand finish plaster with 2 coats of exterior cement paint over one coat of primer.(Brush Finish) |
| |
|
|
|
| 9. |
Terrace |
: |
With Pent Houses, Parapet wall, Lift M/C Room, Staircase Head Room & Over Head Tank & water proofing. |
| |
|
|
|
| 10. |
Parking area
|
: |
In the basement with Cement Flooring, Lift well, Staircase, Electrical Room, Generator Room, Sump, Transformer etc. |
| |
|
|
|
| 11. |
Loft |
: |
One Loft in all bedrooms and kitchen. |
| |
|
|
|
| 12. |
Wardrobes |
: |
Provision in all bedrooms. |
| |
|
|
|
| 13. |
Elecrical |
: |
Concealed copper wiring for Electricity with Skin /Cell make semi modular/equivalent switches with sufficient light, fan, TV, telephone, plug points with standard switch boards.(with Split AC point in MBR & chimney point in Kitchen). |
| |
|
|
|
| 14. |
Common area |
: |
Staircase (Kristal Design), lift, Flooring in common area will be of Granite or equivalent, MS hand rails for Staircase and Corridor, Servant’s Toilet provided in Ground Floor. |
| |
|
|
|
| 15. |
Water supply |
: |
Overhead tank provided with Concealed PVC/GI pipeline along with BWSSB Water line provision in kitchen. |
| |
|
|
|
| 16. |
Sanitary |
: |
Disposal to BWSSB lines; internal PVC lines in ducts. |
| |
|
|
|
| 17. |
Utility |
: |
Provision for Washing Machine. |
| |
|
|
|
| 18. |
Power backup |
: |
Provision for Invertor in all flats. Generator back up for lifts and separate Inverter for Common Area Lighting. |
| |
|
|
|
| 19. |
Intercom |
: |
Intercom facility to all flats and security (Instrument @ extra cost). |
| |
|
|
|
| 20. |
Security |
: |
Security Room will be provided @ necessary locations as per Kristal's Design / requirement. |
| |
|
|
|
| 21. |
Kids Play Area |
: |
Play Area will be provided @ necessary locations as per Kristal's Design / requirement. |
| |
|
|
|
| 22. |
Transformer |
: |
Position of Transformer will be as per Kristal Design after reviewing the Technical Feasibility. |
| |
|
|
|
| |
|
|